Traffic Management on Newbury Road
Northbound:
22 September to 14 October: Night-time road closure between 8pm and 6am. Road open as normal during the day.
Works to be carried out include;
• installation of ducting (protective tubes for cabling)
• construction of new buildouts (where the pavement extends slightly into the road. This narrows the road at that point and encourages drivers to slow down and drive more carefully).
• kerbs
• laying new tactile (bumpy) paving
• resurfacing of the road
Northbound and Southbound:
15 October to 17 October: Night-time road closure between 8pm and 6am. Road open as normal during the day.
Works to be carried out include;
• resurfacing of the road
• painting white lines
• loop cutting (small grooves are cut into the road surface to install sensors used to control traffic lights)
There will be northbound and southbound closure, and a signed diversion route will be in place.
for further information please click on the following link;
Advanced warning signs will be on-site prior to the commencement of the night works, and updates will be available on the scheme webpage;