The works are scheduled to begin on 20th July 2026 and are expected to take up to 8 nights to complete with road closures to through traffic between 20:00 – 06:00hrs. The road will be open outside of these hours.
The resurfacing works will be carried out in phases as follows:
- Phase 1 - London Road to Colenzo Drive (20th July and 22nd July)
- Phase 2 - Colenzo Drive to Batchelors Barn Road (21st July and 22nd July)
- Phase 3 - Batchelors Barn Road to East Street Roundabout (23rd July and 24th July)
While the schedule allows for potential delays, adverse weather or unforeseen circumstances may still lead to short-notice changes. We will make every effort to provide timely updates, although communicating these to the public at short notice can be challenging.
Advance warning signs will be installed before the start of works, and local residents and businesses will have received a letter.
Further details are available at